The power in a data centre

The power chain is the same in a small and a large data centre. Here we go through the parts of the chain and what needs to be decided for each.

The power chain, part by part

Single-line diagram of a data centre Power runs from the grid through the main breaker and distribution board to the UPS, where a rectifier and an inverter with a battery keep the load running through an outage. A bypass routes around the UPS during service. Then rack distribution and the IT load. Grid 3 × 400 V Main breaker Distribution Rectifier Battery Inverter Bypass Rack distribution IT load What we install and service
  1. Power distribution

    Distribution should be selective: a fault in one rack should trip the protection for that rack, not for the whole room. That is settled when the protection is sized.

  2. UPS

    In a double-conversion UPS the rectifier turns alternating current into direct current and the inverter turns it back. The load always gets clean power from the inverter, and in an outage the battery takes over with no transfer time.

  3. Battery

    Runtime is decided by what should happen in an outage. With a generator, the battery only has to carry the load until it has started. Without one, the battery has to last until the servers have shut down in a controlled way.

  4. Bypass

    An external maintenance bypass routes power around the UPS. Without it, the load has to be switched off every time the UPS is serviced or replaced.

  5. Rack distribution

    Servers with two power supplies can be fed from two separate circuits, A and B. One circuit can then be disconnected without the server noticing.

  6. IT load

    Every part above it is sized for the IT load. That is why every design starts with how many kilowatts the room draws today and how much it needs to handle in future.

Example: a room of 50–100 m²

These are guide values. We find out what your room looks like at the site visit.

Racks
10–30
Power per rack
3–8 kW
Total IT load
30–200 kW
Battery runtime with a generator
10–15 min